A project to widen Birnham Woods Drive from two to four lanes from Waterbend Cove to Rayford Road was awarded in mid-January with a contract for 420 days, according to Montgomery County Precinct 3. The completed project will result in two lanes in each direction in addition to a left-turn lane at Birnham Woods and Waterbend and at Birnham Woods and Lexington Boulevard. As of March 18, the contractor had started to prepare the right of way and install storm sewer along parts of Birnham Woods, according to Precinct 3.